Dalmatia Line Rebuild & Foundations
Northumberland County, PA
Construction of a line rebuild in two phases for PPL Corporation. MJE completed the first phase in 2016. Scope of the second phase was broken into five segments. The segments included approximately 16 miles of demolition and installation of conductor and structures, foundations installation, MOLBAB installation, OPGW splice boxes installation, and the removal and installation of OHGW. This project required an extensive environmental planning to protect the ground, the air, and local vegetation.
customer: PPL Corporation
OWNER: PPL Corporation
PROJECT STATUS: Completed