Echo Wind Farm
Pigeon, MI
Engineering, material procurement, and construction (EPC) for a new wind farm including a 34.5/120 kV substation, 73 miles of 34.5 kV underground collection system, foundation conduit and grounding, and tower wiring for the 70 GE 1.6 MW turbines.
customer: Barton Malow
OWNER: DTE Energy
PROJECT STATUS: Completed