Replaced eight and installed two new steel structures. Reconductored two 345 kV, two 138 kV, and static wire. Ten large drilled pier foundations were installed for the new 138 kV line.
QTS – Fisk Line & Foundations
Illinois | 2019 Transmission – MJ Drilling Replaced eight and installed two new steel structures. Reconductored two 345 kV, two 138 kV, and static wire. Ten large drilled pier foundations were installed for the new 138 kV line.