MJ Drilling – Transmission

Rebuild approximately 22 miles of 230 kV line with 954 ACSR conductor, 7/16″ shield wire, and OPGW. Drilled pier and direct embed foundations with steel structures were installed. For more project information, visit ITC’s website.